Some 11 workers of the Ciracas Sub-district Water Resouces (SDA) Executing Unit Task Force, East Jakarta is building a retaining wall on Jalan Lengkeng, RT 08/02, Kelapa Dua Wetan Urban Village, which aims to prevent landslides.

To prevent landslides optimally, we use river stones

It has been carried out since May 10 and is targeted to be finished in 40 days.

Ciracas Sub-district SDA Executing Unit Task Force Coordinator Deby said the retaining wall would have 30 meters long and 30 centimeters wide with 1.5 meters high.

Retaining Wall Repair on Jalan Kotabumi Ujung to Finish Soon

"To prevent landslides optimally, we use river stones," he expressed, Wednesday (5/18).

According to him, the construction could be realized as the workers were previously focused on repairing retaining walls in other locations. Some were also draining the water channels due to a pile of mud.

"This is done manually," he concluded.

Linked News
Popular News indeks
  1. Temporary Crosswalk to Be Built at Tendean Pedestrian Bridge Site

    access_time18-07-2026 remove_red_eye1177 personFakhrizal Fakhri
  2. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1156 personDessy Suciati
  3. Gas Stove Leak Sparks Fire, Gutting Five Rented Houses on Jalan Kayu Tinggi

    access_time17-07-2026 remove_red_eye936 personNurito
  4. Rano Challenges Jakarta Provoke Organizers to Hold Exhibition Along Sudirman-Thamrin

    access_time18-07-2026 remove_red_eye873 personBudhi Firmansyah Surapati
  5. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye841 personDessy Suciati